In the 150th anniversary year of Burlington Baptist Church, Ipswich, the building of a new Annexe is well under way during the Autumn as ground preparations are made and the steel frame built. Check these pages for the latest news and pictures (which will be towards the top of the page). Click the images to see a larger picture.
Please note: The car park is not available whilst the Annexe is being built, please see here for alternative parking arrangements.
Progress
Information and plans | Summer 2006 | Autumn 2006 | Winter 2006/07 | Spring 2007 | Summer 2007 | Autumn 2007 | Winter 2007/08
November 2006
The floor section is manoeuvred into place
The crane swings a floor section over the Church
The crane unloading floor sections
The completed ground floor and first floor steelwork
Two Riggers in cherry pickers bolting high level pieces of steel together
The very first piece of steel being fixed in to place
The very first piece of steel being lifted
The crane unloading the steel
The lorry delivering the steel
New walls showing size of basement
October 2006
The basement walls are nearly full
Giant concrete pump pouring the basement walls
The basement walls being prepared for concrete pouring
The new basement floor (the red markers on the Church wall indicate the final floor level of the Annexe)
The new basement floor (showing the strengthened area by the old Church basement)
September 2006
Foundation trench prepared showing steel reinforcements
Concrete is poured into the foundation trench